House Construction 2009
20 October 2009 : a lot more progress on house :
- Main plumbing complete and water connected.
- Both bathrooms / toilets finished. Separate toilet and basin upstairs finished. We had our first shower (cold) before leaving in August
- All electrical wiring done. Plug sockets and switches fitted
- Waiting for electricity, but people from electricity company visited on 19 Oct
- Staircase finished with marble (marmara) : it looks superb, matching well with the floor tiles
- Interior walls all painted
- Septic tank : hole dug and concrete sections installed, connected and backfilled
15 August 2009 : - Front steps finished
- All doors, windows, roller shutters, mozzie screens in place
- All wiring on ground and top floor done. Basement in progress.
- Ordered bathroom items, toilets, basins etc. To arrive next week
- Started application for eletricity
20 June 2009 : making some progress on house.
- Most of the windows are now installed. Doors to be done next
- Bathroom tiles and roof tiles finished
- Work started on front steps
----------------------------------------------------------------------------------
House - April 2009 .... with windows !
Last year after the construction company stopped work due to their huge debts, we did a bit of work on the house to finish the floor tiles and do some landscaping to steer the winter rain round the house. When we arrived in April the inside of the house was completely dry so we were happy to start some more work on it.
House - April 2009